We are planning to use a tunnel mouth that already exists at Gullmarsplan. The establishment zone will be set up next to the entrance/exit to the tunnel that is being built and is located below the Gullmarsplan underground station beneath the bridges (see map).
Two zones will be fenced in when tunnel construction commences, in spring 2021. These zones will be between 2000 and 4000 sq m in area and are indicated by the black dashed lines in the illustration below. We will be placing site huts, vehicles and materials required for the work in these zones.
Work will take place between the hours of 7am and 10pm on weekdays. The further away from the zone you are, the less disruptive noise you will hear. We will remove the tunnel mouth and restore the area in consultation with the landowner when construction of the tunnel is complete.